Client: PTT Public Company Limited.

527 Views  | 

Client: PTT Public Company Limited.

PTT has implemented for new substation building with working area 684 sq.mm and new power distribution and control system for Onshore Compressor Station Unit 3. The engineering, procurement and construction comprises of several major equipment and related work system as following.

  • Provided engineering and design for civil, architect, electrical and automation, fire protection and building facilities system including permits from government
  • Built up for new substation building including civil, architect
  • Built up for electrical power distribution system and motor control center system.as redundancy system including MV & LV Switchgear and MCC cubicle, transformer, busduct, cables and raceway
  • Built up for control and supervisory (C&S) for utilities system
  • Built up for CO2 fire fighting system
  • Built up for HVAC and ventilation system
  • Build up for DCS system
  • Provided test and inspection plan and tested for all system
  • Tie in for new built up power and control system to existing production process
  • Provide final document and training