Client : PTT Public Company Limited

38 Views  | 

Client : PTT Public Company Limited

PTT Oil and Gas (Rayong) would like to improve the air conditioning system for battery room in GSP#2 substation(hazardous area) in order to extend life time for seal lead battery. Project period is Jan 2023 to May 2023 // Contract amount : 3,000,000 Baht

Our responsibilities are as following details. 

1. Provide engineering and design including air conditioning and ventilation, power distribution and motor control center,  automatic controlling and monitoring by PLC. 
2. Provide calculation for all related design system 
3. Provide JSA, method statement and execute project with safety management policy in hazardous area 
4. Supply and install new equipment for air conditioning system, electrical and automation equipment and programming. 
5. Provide testing and test report for all equipment (insulation, function test, communication loop test and balancing tuning) 
6. Provide final document and training

Powered by MakeWebEasy.com
This website uses cookies for best user experience, to find out more you can go to our Privacy Policy  and  Cookies Policy