Cristalla had built up for Sugar factory and Power Plant in Sukhothai with working areafor 5,500 sq.mm. We had constructed for electrical system as following details.
- Supplied and Installed for LV cables from MDB, MCC, DB panels to machines
- Supplied equipment and installed for LV MDB, MCC, DB , PLC panel, raceway, cable and termination work both power and control system
- Supplied and installed for lighting of landscape area of factory area.
- Test & commissioning and start up plant with SCADA team